Construction of magistral gas pipeline with diameter DN500/75 bars in total lenght of 83 km, including of 275 m of pipeline submerged on the bottom of Krka river – Consortium leading partner for complete construction works
Construction of magistral gas pipeline with diameter DN700/75 bars in lenght of 21 km and diameter DN500/50 bars in lenght of 2 km – Consortium partner for mechanical construction works
High pressure gas pipeline and metering station
16″ dia., 9.5 km, 60.000 Nm3/h
‘Construction of high pressure gas pipeline gas metering/reduction station, block valve, stations, control and regulation system, cathodic protection.